Rig Conditioning Survey

According to API

 Our Aims are:

1-Zero Injuries

2-Zero Down time

3-Optimum performance

What is R.C.S ?

RCS undertakes land rig inspection, condition surveys, rig selection inspection and audits Worldwide. Our detailed surveys provide you with the information you need to enable an informed decision to be made when considering hiring or operating a rig.

Our Inspection formatting provides you with clear and concise technical evaluation for the degree of inspection that you wish to engage.

Applicable Standards and Guidelines

Our Surveying is fully obeying to the following:

1.The original equipment manufacturers maintenance and operating specifications

2.IADC

3.EGPC rules

4.Accepted oilfield practices.

5.API regulations

6.KPC rules.

Compliance with API international requirements used as the basis for these inspections.

Reporting System & Deliverables

Daily reports - emailed to the client requested contacts

A daily report will be prepared and presented to KPC including an INITIAL result & our Recommendations in a frame of Critical, Major and Minor issues found while the visit.

Preliminary Excel report

(Will be submitted 5 working Days After finishing Audit visit)

Final HSE Review Report

(Will be submitted 10 working Days After finishing Audit visit)

Final Survey report to be submitted two days later

(Will be submitted 10 working Days After finishing Audit visit)

Action Plan for findings identified in Discrepancies and recommendation list

(Will be submitted with final survey report)

LIST OF RECOMMENDATIONS

Critical Recommendations are based on shortcomings which may lead to loss of life, a serious injury or environmental damage as a result of inadequate use and/or failure of equipment.

Major Recommendations are based on shortcomings which may lead to damage to essential equipment or have a detrimental effect on the drilling operation as a result of inadequate use and/or failure of equipment.

Minor Recommendations are based on shortcomings which may lead to a situation that contributes to an incident or to circumstances in which the required standards of operation are not met.

Detailed Scope of work

The survey will cover the following areas:

Documentations & Records review

(All Rig components & equipment)

(All Pressurized& atmospheric system)

(All wires/slings, shackles & pad eyes)

(Stand pipe, Kelly hose, Chiksan & HP hoses)

(All gauges in the rig)

(CAT III & CAT IV)

Documentations Recommendations